Adriatic

The Adriatic main line, extending mostly along the eastern Italian cost from Bologna to Lecce/Taranto, connects Northern Italy to Central Europe, with the network of southern Italian ports (Brindisi, Taranto, Gioia Tauro) and makes up an integral part of the system of freight corridors at a European level, known as the “Terfn network”.
In this context, a series of projects were planned, aiming to widen traffic size restrictions providing a route enabling the passage of road vehicles on drop-centre flatcars that have the widest allowed gauges and shipping containers of the “high-cube” type, loaded on carriages with standard floors.
Furthermore, infrastructure work has been planned on this Main line to complete the track-doubling on the stretches that are still single-track with relevant technological work over the whole line, aimed at giving the railway route the performance features necessary to act, in terms of passenger and freight traffic, as a main North-South link in the south-eastern corner of the country. 

The main projects are:
• Adriatic main line tunnel adjustment to gauge C (work on Castellano and Cattolica tunnels)
•  Bologna-Baritechnological upgrade
• Track doubling, Pescara- Bari (includes track doubling in Termoli-Lesina, Apricena-S.Severo and stretch to the north of Ortona)
• Bari – Tarant track doubling (includes track doubling in Bari S.Andrea-Bitetto, Palagianello-Palagiano, bretella Bellavista-Cagioni)
• Bari-Lecce track doubling and electrification

COMPLETED WORK  

Adriatic main line tunnels, adjustment to gauge C     83 MIO € 
Castellano tunnel   2008  

Track doubling on Pescara- Bari   5 MIO €
Lesina-Apricena    2003  
fine detailed design for Termoli-Lesina track doubling   2005
Ortona-Casalbordino     2006
Port of Vasto-Vasto    2006  
Apricena-S.Severo    2007 
executive design for elimination of 4 Level Crossings in Barletta    2008  

 Bari – Taranto track doubling    496 MIO € 
Bitetto-Acquaviva delle Fonti    2005  
Acquaviva delle Fonti- Gioia del Colle    2005  
Massafra-Bellavista-Taranto    2007 
Castellaneta-Palagianello-Palagiano-Massafra    2008  

Bari – Lecce track doubling and electrification    228 MIO €  
Bari – Lecce track doubling and electrification   2006 


WORK IN PROGRESS  

Adriatic main line tunnels, adjustment to gauge C     83 MIO €  
Cattolica tunnel   2011  

Bologna-Bari technological upgrade    295 MIO €  
traffic command and control system (CCS) across the whole line   2010 

Track doubling on the Pescara- Bari     501 MIO €
track doubling north of Ortona    2014  

Bari – Taranto track doubling     496 MIO € 
Bellavista- Cagioni junction  2010  
Bari S.Andrea-Bitetto  2013  

Overall cost for the work is equal to 1603 MIO €.

Further Reading

Attachments

Help  |  Site Map  |  Accessibility Logo attestante il superamento, ai sensi della Legge n. 4/2004, della verifica tecnica di accessibilità.  |  Credits
© Gruppo Ferrovie 2008  |  Contacts  |  Legal Notes  |  VAT Number 05403151003  |  PDM  |  SIGMAP  |  Link