Genoa Hub

Verona hub The Genoa Hub represents a strategic point on the national and international railway network as it constitutes a major interchange centre between the port and railway systems on the Genoa – Ventimiglia, Tirrenica and Milan – Genoa main lines. The hub itself also constitutes the most efficient system for railway travel in the context of the relatively vast metropolitan area.

Planned work aim to: 

• separate traffic flows: long haul passengers and freight from regional and metropolitan passengers
• complete a link between the Liguria port system and the root national network be it east-west or, principally, north-south
• strengthen and automate hub infrastructure and facilities to extend the metropolitan transport supply
• adjust station facilities at Genoa Voltri, Genoa Sampierdarena, Genoa Brignole stations, and adjust services in the Genoa Terralba area and at Genoa Brignole station, to facilitate intramodal and intermodal interchange. 

The work referred-to above divides into the following projects: 

Voltri-Brignole infrastructural upgrade
upgrading Genoa Hub command and control system (the project consists of: remote-controlling the Hub lines from a new Central Control Point, located at Genoa Sanpierdarena, with the activation of a new CCS, as well as of completing infrastructural and technological work towards traffic circulatio with parallel working on the Giovi lines)
modified route on Genoa-Ventimiglia line in the Pegli-Volti stretch
rationalising stretch installations and stops to upgrade the Genoa Hub regional railway service

WORK COMPLETED

 Upgrade Genoa Hub command and control system  167 MIO €
 Central Control Point, command and control system for governing unit and parallel workings  2006

 Modifying the Genoa-Ventimiglia line on the Pegli-Voltri stretch  39 MIO €
building modified Pegli-Voltri route, including the new Pra stop  2006

 Rationalising installations and stops for the upgrade of the Genoa Hub regional railway service  17 MIO €
 new San Biagio and Via di Francia stops 2005
 new Mignanego ESS  2007 

 WORK IN PROGRESS

Voltri-Brignole infrastructural upgrade  622 MIO €
 in 2006, the CIPE approved the final detailed design for the project; Italferr has drawn up the executive design and by 2008 will open bidding proceedings  activations in functional phases 2015

 Modification to the Genoa-Ventimiglia line in the Pegli-Voltri stretch  39 MIO €
 completing Voltri yard  2009

 Rationalising installations and stops to upgrade the Genoa Hub regional railway service  17 MIO €
new Genoa Teglia stop  2014

Overall cost of the work is equal to 845 MIO €.

Further Reading

Attachments

Help  |  Site Map  |  Accessibility Logo attestante il superamento, ai sensi della Legge n. 4/2004, della verifica tecnica di accessibilità.  |  Credits
© Gruppo Ferrovie 2008  |  Contacts  |  Legal Notes  |  VAT Number 05403151003  |  PDM  |  SIGMAP  |  Link